The new broad gauge rail line of 10.65 km between Bichhupali and Jhartarbha of Khurda Road-Balangir Rail Line project has been completed and commissioned.
Commissioner Railway Safety (CRS) inspected the rail line on November 10 and had given his consent for commissioning.
CRS also inspected the safety aspects thoroughly before declaring it fit for the purpose for 10.65 km line of the on-going 289 km Khurda Road-Balangir Rail line project.
Also read: Roop Narayan Sunkar is new general manager of ECoR
A team of senior railway officials of ECoR assisted CRS during the inspection. They inspected different railway components along with the gauge measurement.
Railways has been constructing the line from both the sides – from Khurda Road and Balangir for the early completion of the project.
East Coast Railway is committed for development of railway infrastructure in the region and working dedicatedly to complete the project before the target.
Kolkata: ZODIAC, a leading name in premium fashion, has introduced its much-anticipated 2024 Positano Collection,…
New Delhi: Birla Fertility & IVF, a leading IVF network in India and part of…
Multi-gym equipment at the newly inaugurated Mo Gym & Cafe in Cuttack. Cuttack got its…
Doctors and experts during the launch of ProPainTA in Bhubaneswar. Bhubaneswar: In a significant stride…
BJEM School-1 strike a pose after winning the Intra School Cricket Tournament. (Photo: OCA) Bhubaneswar:…
A skill development camp underway at Cuttack CDA DAV campus. (Photo credit: OCA) Cuttack: The…